A proposed $936,000 contribution from Ausgrid’s Steel River East Battery Energy Storage System at Mayfield West could help fund solar panels and battery storage at Newcastle’s public buildings and facilities.

City of Newcastle has placed a draft planning agreement with Ausgrid on public exhibition, proposing that the contribution be used to support solar installations and/or batteries at council facilities, including the Civic Theatre, Newcastle Museum, Art Gallery and public libraries.

The agreement is associated with the 200 MW, 400 MWh Steel River East Battery Energy Storage System, which received development consent from the NSW Independent Planning Commission in March 2026.

The project is proposed for 1 McIntosh Drive, Mayfield West, in Newcastle’s Steel River industrial precinct.

Under the draft agreement, Ausgrid would make a one-off contribution of $936,000, excluding GST and subject to indexation, towards renewable energy installations at council facilities.

Seven council facilities identified

City of Newcastle’s September council report identifies seven potential locations for battery installations, with indicative storage capacities ranging from 260 kWh to 520 kWh.

The Civic Theatre and Newcastle Art Gallery are each identified for potential 520 kWh batteries, while Waratah Works Depot, Newcastle City Library, Newcastle Museum, Wallsend Library and No. 2 Sportsground are each listed with indicative capacities of 260 kWh.

Together, these indicative capacities total 2.34 MWh of battery storage. However, the locations, capacities and number of installations remain subject to detailed design, approvals, applicable funding conditions and future council budget decisions.

According to City of Newcastle, the proposed installations would support the electrification of council operations and its transition to renewable energy.

Agreement linked to battery development approval

The Steel River East battery project received planning consent in March 2026, with a condition requiring Ausgrid to enter into a planning agreement with City of Newcastle before construction begins, unless the NSW Planning Secretary agrees otherwise.

The proposed contribution was negotiated using a benchmark from the NSW Government’s Benefit-Sharing Guideline, calculated over an assumed 20-year project life and converted into an upfront payment.

Although the guideline does not formally apply to battery projects on non-rural zoned land, Ausgrid used its published rate as a basis for calculating the proposed contribution.

The September council report states that the contribution would be allocated towards the public purpose specified in the final planning agreement, rather than being available for general council expenditure.

The draft agreement provides for the contribution to be used towards solar installations and/or batteries at council facilities. It also contains provisions allowing council to apply the contribution to another public purpose if it reasonably considers that doing so would better serve the public interest.

City of Newcastle has separately secured $5 million from the Australian Renewable Energy Agency (ARENA) through its Community Batteries Funding Round 2.

The proposed Ausgrid contribution is separate from that funding and is intended to complement the council’s renewable energy activities.

Public submissions open until 1 December

The draft planning agreement and explanatory note are available for public comment until 5pm on Tuesday 1 December 2026.

The exhibition period, which began on 3 November, provides an opportunity for community members to comment on the proposed agreement before it is finalised.

Submissions can be made through City of Newcastle’s online consultation form.

For more information, visit City of Newcastle’s public notices page, or make a submission.